rail

Our projects

Blackfriars Thameslink Project - Bridge 410E Replacement UK

Scheming and detailed design of a mainline railway bridge replacement scheme within Blackfriars Station in London, UK. 

The project included the following works:

  • Underpinning and strengthening of the existing bridge foundations;
  • Preliminary design of the temporary slide beam and towers;
  • Temporary props for the permanent works to ensure stability in the temporary condition;
  • Design checks of the permanent works for the temporary condition;
  • Detailed design of a temporary rail bridge.

This was done as part of our ongoing post contract award work with the contractor.

Client: Balfour Beatty Civil Engineering Ltd

Country: UK

Year Completed: 2011

Construction Value: