Farringdon Thameslink Project - Temporary Works Design
In order to facilitate construction of this complex station working around London Underground and Thameslink tracks the joint venture contractor engaged us to undertake an assessment of an existing overbridge for storage and accommodation use. We undertook an inspection of the bridge during a pre-planned weekend possession and then prepared an assessment of the structure based on its actual condition and the contractor's intended usage.
Client: Costain - Laing O'Rourke JV
Country: UK
Year Completed: 2011
Construction Value:


Project datasheet